Usin pert adam munson was able to determine that the


Usin PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 16. what is the probability that the project will be completed in eight months, what is the probability that the project will be completed in 23 months, what is the probability that the project will be completed in 28 months, what is the probability that the project will be completed in 40 months? The due date that yields a 95 percent chance of completion equals how many months?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Usin pert adam munson was able to determine that the
Reference No:- TGS02599102

Expected delivery within 24 Hours