If there are no other parts or dependencies what is the


Each product R requires 1 of Part 5 and 3 of Part T. Each 5 requires 3 of Part U. It takes 3 days to assemble Product R. It takes 6 days to assemble Part 5. It takes 9 days and 10 days to procure Parts T and U respectively. If there are no other parts or dependencies, what is the total time to produce Product R?