Layt Clock Company has developed the following flexible budget for its overhead costs. The standard hours allowed per unit is 1.2 hours. Manufacturing overhead at Layt is applied to production on the basis of standard machine-hours:


Budget Information



Machine Hours

26,400


Clocks produced..................

22,000


Variable overhead cost per machine hour (standard) ..

$5.90


Fixed overhead cost per unit per machine hours (standard)

$6.48


Total Fixed overhead cost....

$171,072

The actual results for the year were as follows:


Number of clocks produced..........

21,500


Machine-hours incurred.................

24,940


Variable overhead cost..................

$145,899


Fixed overhead cost......................

$170,540

Required:

  1. Compute Variable Overhead Rate Variance.

  2. Compute Variable Overhead Efficiency Variance.

  3. Compute Fixed Overhead Budget Variance.

  4. Compute Fixed Overhead Volume Variance.