Determine the direct labor budget for 2012


Sweet Dreams, Inc. manufactures bedding sets. The budgeted production is for 47,800 comforters in 2012. Each comforter requires 1.5 hours to cut and sew the material. If cutting and sewing labor costs $16.00 per hour, determine the direct labor budget for 2012.