Question: When can an uncertainty be closed? (Select all that apply) Question options: When addressing actions are unsuccessful and the uncertainty is still capable of having a high severity impact on project objectives. When it is fully mitigated or reduced to the green level and neglected after all planned addressing actions are completed. When it is fully transferred (e.g., good insurance policy purchased with no or very low deductible). When it is avoided and no longer relevant to the project (e.g., new reference case, change of design, etc.). When the uncertainty is still relevant (e.g., permits not yet received). Need Assignment Help?