Tasks with priority relationship


Problem:

The construction of a cottage requires the performance of certain tasks. The following table lists the various tasks with their priority relationship.

Activity    o     m     p      Predecessors

A             8     10   12         None
B             6      7     9          None
C             3      3    4           None
D           10     20   30            A
E             6       7    8             C
F             9      10  11          B,D,E
G            6        7  10          B,D,E
H           14      15  16             F
I            10      11  13             F
J             6        7    8           G,H
K            4        7    8            I,J
L             1        2   4            G,H

a. Calculate slack for each activity.

b. What is the critical path?

c. What is the project duration?

d. Determine the probability that the project will be finished in 80 days or less.

Solution Preview :

Prepared by a verified Expert
Marketing Management: Tasks with priority relationship
Reference No:- TGS02022149

Now Priced at $25 (50% Discount)

Recommended (97%)

Rated (4.9/5)