Phases and milestones report from projects in progress


Problem: If you are building 3 phases and milestones report from Project's In Progress, Milestone Report, what fields do you want to include in the table associated with the graph?

Select an answer:

  • add Status, retain Start, add Finish. retain 5% Complete
  • retaining Start and Baseline Finish. add Status, retain % Complete
  • add Status, change Start to Baseline Finish, retain Finish and % Complete
  • retain Start and Finish, add Baseline Finish, retain % Complete