How do you determine which Work Breakdown Structure (WBS) elements are at risk of causing the slip? Which is the correct solution?

Analyze the Integrated Master Schedule (IMS) critical path and review the remaining float on slipping tasks

Conduct various Integrated Master Schedule (IMS) schedule health checks and Integrated Program Management Rep validation checks

Sort on major cost variances in the Integrated Program Management Report (IPMR) Format 1 Use technical performance measure (TPM) analysis to identify technical drivers