Development of a core component


Problem:

In a fixed time and budget project, the customer wants the development of a core component to be based on agile practices, as the final scope of the requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project. Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose 2)

  • Establish a governance committee to review the contract delivery. Require that only internal resources be utilized for this project. Limit the number of iterations for development in the contract. Provide alternatives to scope change at specific project phases within the contract.
  • Tier the contract for fixed and agile components.

 

Request for Solution File

Ask an Expert for Answer!!
Other Management: Development of a core component
Reference No:- TGS03421594

Expected delivery within 24 Hours