Define project scope a stakeholder tells the project manager


Problem:

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented in

  • The lessons learned. What should the project manager do?
  • Ask the sponsor to close the project and pay the contracted penalty.
  • Check with the team to learn what can be done, and consult an expert.
  • Check that this information was documented correctly. Meet with the sponsor to ask for their support.

Request for Solution File

Ask an Expert for Answer!!
Other Management: Define project scope a stakeholder tells the project manager
Reference No:- TGS03421598

Expected delivery within 24 Hours