Determine minimum cost to complete project


Data for Time-Cost CPM Scheduling model analysis are listed below. Times are in days. Determine minimum cost to complete this project in 14 days?

Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash cost
A None 4 2 2000 4000
B A 4 3 3000 6000
C A 2 1 2000 2500
D B and C 4 2 5000 5600
E D 3 1 6000 9000