Create aon project network and calculate activity slack


From the information given below, create AON project network. Complete forward and backward pass, calculate activity slack, and recognize the critical path. How many days will project take?

ID Description Predecessor Time
A Identify Topic None 1
B Research Topic A 10
C Draft Paper B 4
D Edit Paper C 4
E Create Graphics C 2
F References C 1
G Final Draft D, E, F 3