Calculate the variable overhead spending and efficiency


Bright Spark Ltd is a manufacture of the electrical switches, and uses a standard costing system. the standard manufacturing overhead costs per seitch are based on labour hours and are as following:

  • variable overhead (5hours @ $12 per hour) $60
  • fixed overhead (5 hours @ $18 per hour) 90
  • total overhead $150
  • based on capacity of 300000 direct labour hours per month
  • the following information is available for month of October:
  • 56000 switches were produced, although 60000 switches were budgeted.
  • 275000 direct labour hours were worked at a total cost of $3825000.
  • variable overhead costs were $3510000.
  • fixed overhead costs were $5625000

required:calculate the variable overhead spending and efficiency variance and the fixed overhead budget and volume variance for October. Indicate whether each variance if favourable or unfavourable.