Discuss the following:
Q: A project manager contracted a supplier to provide 1000 units at an estimated manufacturing cost of $12 each at the rate of 100 units per week for the total duration of the supplier contract of 10 weeks. After four weeks, the supplier delivered 380 units and was very happy to discover that the units only cost $10/unit. Calculate:
Current project status after four weeks:
Project at completion: