questionin designing of watermain regular practice is to use supple iron for pipe size less than 600mm and to use steel for pipe size additional than
questionwhy are two gate regulators necessary in regular practice to form washout regulatorsanswerin fact situation is analogous to that of fire
questionafter construction of watermain earlier to hydrostatic pressure test swabbing is approved out what is main purpose of swabbinganswer
determine the change in ic from 25186c to 175186c for the transistor defined in this table for fixed-bias with rb 240 k and 100 due to the
i got a graduate level database assignment which is due at dec 8 1159pm can you finish it on time in high
questionin designig of watermains how to decide usage of double air valves and single air valvesanswer single air control device let squeezing air
questionshould reversible moisture movement be taken into account in estimating movement for movement jointsanswer size of concrete is affected by
questionwhile designing reservoirs indirect tensile strength of the concrete mix is particular to be less than a specific value such as 28nmm2 for
questionwhy do bs8007 specify permissible crack width of water retaining structure as 02mm for severe extremely severe exposureanswerfor break width
questionwhile selection of waterstop shall engineers use plain dumb-bell type center-bulb sortanswer plain dumb-bell kind is used for joint site
questionwhat is importance of critical steel ratio in scheming thermal reinforcementanswer execution of critical steel ratio resources that in
questionwhat is key principle of adding cooling pipes or yet using cold water for concrete in concreting operationanswerthese methods aim at reducing
questionwhile designing water storage tank has movement joints be installedanswer while designing water storage tanks group joints can be set up in
questionwhat are main functions of slip joints in block work seawallsanswer slip joints are joints that are formed during a complete vertical plane
questionfor fixing of silt curtains what is the reason that it does not desirable to design the curtain to touch the seabedanswer silt finished are
questionwhat are major considerations in selecting marine plants and land plants for fitting of band drainsanswer for fitting of band drains by
questionin search reclamation what are considerations in choosing between trailer suction hopper dredgers and grab dredgersanswer trailer suction
questionif in case a road passes from side to side a reclaimed land and an existing land what is key main concern regarding design of pavementsanswer
questionfor drained reclamation what will significance of smear zone bring by installation of band drainsanswer throughout installation of band
questionwhat is major dissimilarity between standpipe standpipe piezometer and piezometeranswer standpipe usually contains plastic pipes with
questiongeotechnical instrumentation is often employed for monitoring state of reclamation from time to time two piezometers are installed inside
questionwhat is main importance of geotextiles and sand in reclamation worksanswerfor geotextiles used in recovery they serve mainly subsequent two
questionif in case mud waves occur during reclamation what are probable solutions to rectify the situationansweri option 1 - complete removal of all
questionin conditions of pumping performance how have to engineers determined use of radial flow pumps and axial flow pumpsanswer exact speed is
questionwhat is key distinction in arranging pumps in series and in parallelanswer for same pumps with similar functions if pumps arranged in series