Your project is progressing well in your estimation your


Your project is progressing well in your estimation. Your team has collected the following data. From these data, calculate the project’s ETC.

Activity A is 60% complete at a cost so far of $50,000. It was estimated to cost $200,000 when finished. It is at the end of Week 3 of 5. Activity B is 85% complete at a cost so far of $150,000. It was estimated to cost $80,000 when finished. It is at the end of Week 4 of 5. Activity C is complete at a cost so far of $110,000. It was estimated to cost $100,000 when finished. Assume spending will continue at the same rate.