You will be creating a schedule for your project bathroom


In this assignment, you will be creating a schedule for your project (bathroom remodeling)that is in a suitable format to be presented to third parties, including your project sponsor or executives.

Project Name Remodel Master Bathroom

Project Sponsor(s)Andy and Alice Wonder

Proposed Start Date February 01, 2018

Proposed End DateFebruary 23, 2018

Project Purpose

The homeowners, Andy and Alice Wonder, requesting that their master bathroom at 2277 Beverly drive, Palm Spring, CA 92258 The bathroom is currently functional, and the owners just want to remodel the bathroom for appearances and to add value to their home.

Project Description

The remodeling will be done only in the Master bathroom and will include, but is not limited to installing a new toiletoInstalling a new tuboInstallinga new showeroInstalling new cabinets and vanitiesoNew light fixtures new tile for the floor one mirrored plumbingoPaintingof all the walls

Both Andy and Alice Wonder must first approve any new installments

Budget up to $12000