You notice your project schedule is starting to slip and


You notice your project schedule is starting to slip and you would like to reassign some resources. What is one of the first steps you should take?

a. Talk with the project team members.

b. Review the activity duration estimates.

c. Identify future activities that have float.

d. Crash the schedule.