You are preparing an estimate of the cost of an it system


You are preparing an estimate of the cost of an IT system expansion for a new branch offic location. It is a very similar to the IT system expansion undertaken for a branch office that opened six months ago. Which technique might you use if you are pushed for a quick estimate?

a. Parametric

b. Analogous

c. Bottom up

d. Probabilistic

Request for Solution File

Ask an Expert for Answer!!
Operation Management: You are preparing an estimate of the cost of an it system
Reference No:- TGS01385286

Expected delivery within 24 Hours