You have been hired to lead a project the project of your


You have been hired to lead a project (the project of your choice). As the project manager, you know it is important to get the project off to a good start. Using the tools provided in the required readings, provide a quick summary of your project, including the scope and objectives of your project. Be sure to include a high-level WBS for your project.

Example below:

PROJECT OBJECTIVE

To construct a high-quality, custom home within five months at cost not to exceed $500,000.

DELIVERABLES

    A 2,200-square-foot, 2½-bath, 3-bedroom, finished home.

    A finished garage, insulated and sheetrocked.

    Kitchen appliances to include range, oven, microwave, and dishwasher.

    High-efficiency gas furnace with programmable thermostat.

MILESTONES

    Permits approved—March 5

    Foundation poured—March 14

    Drywall in. Framing, sheathing, plumbing, electrical, and mechanical inspections passed—May 25

    Final inspection—June 7

TECHNICAL REQUIREMENTS

    Home must meet local building codes.

    All windows and doors must pass NFRC class 40 energy ratings.

    Exterior wall insulation must meet an “R” factor of 21.

    Ceiling insulation must meet an “R” factor of 38.

    Floor insulation must meet an “R” factor of 25.

    Garage will accommodate two large-size cars and one 20-foot Winnebago.

    Structure must pass seismic stability codes.

LIMITS AND EXCLUSIONS

    The home will be built to the specifications and design of the original blueprints provided by the customer.

    Owner is responsible for landscaping.

    Refrigerator is not included among kitchen appliances.

    Air conditioning is not included but prewiring is included.

    Contractor reserves the right to contract out services.

    Contractor is responsible for subcontracted work.

    Site work limited to Monday through Friday, 8:00 A.M. to 6:00 P.M.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: You have been hired to lead a project the project of your
Reference No:- TGS01678470

Expected delivery within 24 Hours