You are the project manager of a home improvement project


You are the project manager of a home improvement project.   One of the work packages in your plan called for painting 10 equally sized rooms.   The budgeted cost of this work package was a total of $2,000.   In your team meeting you are told that 6 of the rooms have been painted.   What is the earned value (EV) of the work completed?