You are the project manager for a large software


You are the project manager for a large software development project. You have concerns that one of the components of the Iron Triangle is slipping. Your project sponsor, Jim Bob, is not familiar with the Iron Triangle, so you explain the concept to him. What will be affected if any angle of the Iron Triangle is not kept in balance?

A.  Cost

B.  Quality

C.  Time

D.  Scope