You and your project team are located in des moines iowa


You and your project team are located in Des Moines, Iowa, but your project execution will take place in Mexico. You have valid concerns about the interactions with the stakeholders, including time zone differences; language barriers; the different laws that could affect your project; and the logistics of travel, face-to-face meetings, and even teleconferencing. Which of the following project environments are you concerned with most?

A.  Cultural and social

B.  International and political

C.  Physical

D.  Organizational structure