You are preparing to budget for a major task in the project


You are preparing to budget for a major task in the project. The work element will require 200 hours of labor by a qualified individual. The worker with the appropriate level of training is paid $38.50 per hour. The company adds 76% for overhead costs, and an additional 20% for G&A costs. If your company requires workers to receive 15% personal time, what is the value of the fully costed work element?