You are given these cash flows for an investment project


1. You are given these cash flows for an investment project shown below:

0: -$200,000

1: +$110,000

2: +$121,000

The internal rate of return (IRR) of the project is _____.

a) 5%

b) 15%

c) 1.155%

d) 10%

2. You are given these cash flows for an investment project (the time 0 cash flow is missing):

0: _______

1: +$115,000

2: +$132,250

If the required return (cost of capital) is 15%, and the net present value (NPV) of the project is +$25,000, what is the missing time 0 cash flow?

a) -$150,000

b) -$175,000

c) -$197,250

d) +$150,000

Request for Solution File

Ask an Expert for Answer!!
Financial Management: You are given these cash flows for an investment project
Reference No:- TGS02674077

Expected delivery within 24 Hours