You are comparing two projects using the data below


You are comparing two projects. Using the data below, calculate the CV, SV, SPI, and CPI. Second, use the values to provide the status of each project. All values are in dollars.

Project A EV 650 PV 750 AC 675

Project B EV 550 PV 575 AC 525