xcell engineering is planning to construct a


Xcell engineering is planning to construct a futsal stadium which has 5 courts to be rented out at any point of time. Its initial cost of investment is RM$280,000. It is expected to generate sales of RM$20,000 per court for year one and a 10% increase for every year from year 2 to year 5. The operating cost for year one for per court is RM$7,000 and it also expected to increase by 10% each year from year 2 to 5. At year 5 it can cease operation by selling the business to Mr.Free for RM$280,000. The cost of capital is 10%. Will you recommend this project to be financed by your company? Use NPV method to show your calculations.