Xander company anticipates that usage of component t will


Part A:

1. Xander Company anticipates that usage of Component T will be 100 units daily, which equates to around 25,000 for the year. The material is expected to cost $5 per unit. Once an order is placed with its vendor, it takes five days to receive the goods, and the cost of placing each order is $50. As a result, Xander keeps 1,000 units on hand to avoid stockouts. The carrying cost associated with each unit is $10.

a. Compute the order point.

b. Determine the most economical order quantity.

2. Consider the following cost production summary for carrigan products for May

Carrigan Products
Cost of production Summary
For the Month Ended May 31, 20-------

Cost of work in process, beginning of month:
Materials $8,200
Labor 5,500
Factory overhead 2,000 $15,700
Cost of production for month:
Materials $24,000
Labor 17,600
Factory overhead 16,900 58,500
Total costs to be accounted for $74,200
Unit output for month:
Finished and transferred to finished goods 2,000
Equivalent units of work in process,
end of month (1,000 units, 80% completed) 800
Total equivalent production 2,800
Unit cost for month:
Materials [($8,200 + $24,000) ÷ 2,800] $11.50
Labor [($5,500 + $17,600) ÷ 2,800] 8.25
Factory overhead [($2,000 + $16,900) ÷ 2,800] 6.75
Total $26.50
Inventory costs:
Cost of goods finished and transferred to
finished goods during month: (2,000 × $26.50) $53,000
Cost of work in process, end of month:
Materials (1,000 × .8 × $11.50) $9,200
Labor (1,000 × .8 × $8.25) 6,600
Factory overhead (1,000 × .8 × $6.75) 5,400 21,200
Total production costs accounted for $74,200

3. Perez Company adopted a standard cost system several years ago. the standard cost for the prime costs of its single product follow:

Material: 10 kg @ $4.50 per kg $45.00

Labor: 6 hours 2 $ 8.50 per hour $ 51.00

The following operating data were taken from the records for November.

(1) Units completed : 5,800 units
(2) Budgeted output : 6,000 units
(3) Materials purchased: 60,000 kg
(4) Total actual labor costs: $306,600
(5) Actual hours of labor: 36,500 hours
(6) Materials quantity variance: $2,250 unfavorable
(7) Materials price variance: $,800 favorable
Compute the following
a) Labor rate variance
b) Labor efficiency variance

Part B.

1. What is the business entity that converts purchased raw materials into finished goods by using labor, technology, and facilities?

2. What considerations should an effective cost control system include? (name four of the six considerations)
Rep:

3. What type of wage plan is based solely on an employee's quantity of production?

4. Which costs vary in direct proportion to volume changes?

5. What costing techniques should be used in assigning costs to products if the product is composed of mass-produced homogenous units?

6. How are normal losses that occur in the manufacturing process properly classified when considered as part of the total cost of production?

7. What type of budget is prepared for a single level of volume based on management's best estimate of the level of production and sales for the coming period?

8. What is the purpose of standard costing?

9. What type of report compares the budgeted cost for the job to the actual costs incurred and indicates the variances?

10. On a variable costing income statement, what is the difference between sales and variable cost of goods sold?

Solution Preview :

Prepared by a verified Expert
Finance Basics: Xander company anticipates that usage of component t will
Reference No:- TGS01249389

Now Priced at $50 (50% Discount)

Recommended (97%)

Rated (4.9/5)