Which one of the following is not an example of an


Which one of the following is not an example of an Organizational Process Asset?

A) Procedures used for authorizing work

B) Templates

C) Policies and procedures

D) Microsoft Project 2007

E) Financial controls

Activities that must occur immediately before a given activity are called ________ activities.

A(n) ________ is the minimum amount of time a dependent activity must be delayed to begin or end.

Joe is looking at a document that outlines the specific tasks and subtasks required to complete the writing of a technical support manual. The method that was probably used to develop the document is most likely:

A) Responsibility matrix

B) Organization breakdown structure

C) Work breakdown structure

D) Priority matrix

E) Work package

The first step in creating the necessary information to manage a project is to:

A) Establish project priorities

B) Define the project scope

C) Verify the budget available

D) Assign team members to work on the project

E) Determine the required completion date

In Microsoft Project, if a resource is scheduled for more work - in a given time period - than that resource can accomplish, the resources is:

A) Maximized

B) Constrained

C) Overallocated

D) Late

E) Working overtime