All of the following are true about work packages except


All of the following are true about work packages except:

A) Consume resources

B) Assigned to only one manager

C) Have medium to long duration

D) Definitive starts and stops dates

E) All of these are true

All of the following are usually included in a work package except:

A) What will be done?

B) The time needed to complete the work.

C) A single person who is responsible for its completion.

D) All the costs for the work package.

E) All of these are included in a work package.

The project scope statement indicates that the client is responsible for training the people who will be using the equipment and that the project team will train the client's trainers. This is an example of:

A) Project objectives

B) Deliverables

C) Limits and exclusions

D) Technical requirements

E) Milestones

The tendency for the project deliverables to expand over time - usually by changing requirements, specifications, and priorities - is called:

A) Scope erosion

B) Scope creep

C) Project bloat

D) Scope enhancement

E) Project add-ons

Request for Solution File

Ask an Expert for Answer!!
Other Subject: All of the following are true about work packages except
Reference No:- TGS0660620

Expected delivery within 24 Hours