Which of the following statements is incorrect regarding


1. Which of the following statements is INCORRECT regarding the theoretical minimum number of workstations in assembly balancing? It is the ratio of the sum of all task times to required cycle time It is always less than the actual number of workstations to be used. It is always (when a fraction) rounded up to the next larger integer value It is not always possible to reach when tasks are assigned to stations in reality

2. Which of the following production layouts is recommended for low-volume production of non-standardized products?

Product layout

Process layout

Fixed-position layout