Which method for developing the mine should be used


Problem

One method for developing a mine containing an estimated 100,000 tons of ore will result in the recovery of 62% of the available ore deposit and will cost $23 per ton of material removed. A second method of development will recover only 50% of the ore deposit, but it will cost only $15 per ton of material removed. Subsequent processing of the removed ore recovers 300 pounds of metal from each ton of processed ore and costs $40 per ton of ore processed. The recovered metal can be sold for $0.80 per pound. Which method for developing the mine should be used if your objective is to maximize total profit from the mine?

The response should include a reference list. Double-space, using Times New Roman 12 pnt font, one-inch margins, and APA style of writing and citations.

Request for Solution File

Ask an Expert for Answer!!
Microeconomics: Which method for developing the mine should be used
Reference No:- TGS02127011

Expected delivery within 24 Hours