Which costing system more accurately assigns to jobs


Problem:

Harris Systems specializes in servers for workgroup, e-commerce, and ERP applications. The company's original job costing system has two direct cost categories: direct materials and direct labor. Overhead is allocated to jobs at the single rate of $22 per direct labor hour. A task force headed by Harris's CFO recently designed an ABC system with four activities. The ABC system retains the current system's two direct cost categories. Overhead costs are reflected in the four activities. Pertinent data follow:

Activity

Number of parts

Cost Allocation Rate

Materials handling

Number of setups

$ 0.85

Machine setup

Assembling hours

500.00

Assembling

Number of shipments

80.00

Shipping

Allocation Base

1,500.00

Harris Systems has been awarded two new contracts, which will be produced as Job A and Job B. Budget data relating to the contracts follow:


Job A

Job B

Number of parts

15,000

2,000

Number of setups

6

4

Number of assembling hours

1,500

200

Number of shipments

1

1

Total direct labor hours

8,000

600

Number of units produced

100

10

Direct materials cost

$220,000

$30,000

Direct labor cost

$160,000

$12,000

Requirements

1. Compute the product cost per unit for each job, using the original costing system (with two direct cost categories and a single overhead allocation rate).

2. Suppose Harris Systems adopts the ABC system. Compute the product cost per unit for each job using ABC.

3. Which costing system more accurately assigns to jobs the costs of the resources consumed to produce them? Explain.

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Which costing system more accurately assigns to jobs
Reference No:- TGS02038125

Now Priced at $20 (50% Discount)

Recommended (93%)

Rated (4.5/5)