What should the project lead ask the project team do


Question: During a sprint, one of the team members found an issue. According to the team member and the product owner, the issue has a higher level of importance than the other features of the sprint, but is not a roadblock to completing it. What should the project lead ask the project team do?

O Address this issue only as it has a higher priority than the remaining features of the same sprint.

O Submit the issue to the change control board (CCB) to evaluate and formally approve a plan to address it.

Avoid the temptation to make any changes and address the issue in the next sprint. Follow the sprint plan by delivering the features established for the sprint and prioritize the issue in the backlog.

 

 

Request for Solution File

Ask an Expert for Answer!!
Other Management: What should the project lead ask the project team do
Reference No:- TGS03422007

Expected delivery within 24 Hours