What sequence of activities make up the critical path


Problem

A simple project listing of five activities and their respective time estimates are presented here:

Activity

Immediate Predecessor

Time (days)

A

none

1

B

A

2

C

A

1

D

B and C

3

E

D

2

a) Using the Critical Path Method, draw the activity network diagram.

b) What sequence of activities make up the critical path?

c) How many days should the project take?

Request for Solution File

Ask an Expert for Answer!!
Other Subject: What sequence of activities make up the critical path
Reference No:- TGS03329476

Expected delivery within 24 Hours