What method should be used using only one pseudo-activity


Homework: Project Scheduling 1) A company decides to plan a project, with activities, precedences and deterministic durations given in the following table: Activity i Duration (days) Immediate Predecessors A 32 none B 21 none C 30 none D 45 A E 26 A, B F 28 C G 20 E, F Answer the following questions:

1.1) What method should be used? Using only one pseudo-activity, draw the project network, with arcs labeled by the activity name and duration.

1.2) Compute and display in a table the earliest and latest starting and finishing times, as well as slack, for each activity, and identify the critical path(s).

1.3) Draw a Gantt chart of the schedule, based on earliest starting times

1.4) Which activities must be completed by day 60 to ensure that the project is not delayed?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What method should be used using only one pseudo-activity
Reference No:- TGS02533984

Expected delivery within 24 Hours