What is the total cost over the twelve-day planning horizon


Problem: RESTWELL SCHEDULING

The Restwell Motel in Orlando, Florida, is preparing an aggregate plan for the upcoming twelve days. The motel has a maximum of 200 rooms, but demand varies during the week. Demand is listed in terms of rooms rented each day. The motel requires one employee, paid $105 per day for each 12 rooms rented on regular time. It can utilize up to 20 percent overtime at time and a half and also can hire part-time workers at $120 per day. Each part-time worker can also clean 12 rooms per day. There is no hiring and layoff cost for the part-time workers. A fractional number of part-time workers (e.g., 3.4 workers) can be employed since less than a full day of employment is possible for each worker.

Day M T W Th F S Su M T W Th F
Demand 185 190 170 160 110 100 100 160 180 170 150 100

• Assume a steady regular workforce of 10 employees, 20 percent overtime when needed, and the balance of demand met by part-time workers. How much does this strategy cost over the 12-day planning horizon. When needed to meet demand, assume maximum overtime is used before part-time workers are hired.

• What is the total cost over the 12-day planning horizon if the regular workforce of 10 employees and only part-time workers are used? No overtime is used?

The response should include a reference list. Double-space, using Times New Roman 12 pnt font, one-inch margins, and APA style of writing and citations.

Solution Preview :

Prepared by a verified Expert
Operation Management: What is the total cost over the twelve-day planning horizon
Reference No:- TGS03052861

Now Priced at $30 (50% Discount)

Recommended (99%)

Rated (4.3/5)