What is the net present value of the project


Problem

Jimenez, Incorporated, is an all-equity firm. The cost of the company's equity is currently 11.2 percent and the risk-free rate is 3.4 percent. The company is currently considering a project that will cost $11.6 million and last six years. The company uses straight-line depreciation. The project will generate revenues minus expenses each year in the amount of $3.5 million. If the company has a tax rate of 23 percent, what is the net present value of the project?