What is the estimated total duration for the project


Activity Problem

Activity 1

Your university is holding a fund-raiser and will be hiring a band to entertain spectators. You have been selected to serve as the event project manager and have created a Work Breakdown Structure and duration estimates for the activities involved in site preparation for the event. Construct a network activity diagram based on the following information:

Activity Description Predecessors Duration (Days)

Activity

Description

Predecessors

Duration (Days)

A

Site selection

None

4

B

Buy concessions

A

4

C

Rent facilities

A

2

D

Build stands

A

5

E

Generator & wiring installation

C

2

F

Security

B

4

G

Lighting installation

E

2

H

Sound system installation

E, F

2

I

Stage construction

D

3

J

Tear down

G, H, I

4

• Conduct both a forward and backward pass using AON notation. What is the estimated total duration for the project?
• Identify all paths through the network. Which is the critical path?
• Which activities have slack time?
• Identify all burst activities and merge activities.

Activity 2

Given the following information, answer the questions about this project:

Activity

Expected Duration

Predecessors

A

4 days

-

B

9 days

A

C

11 days

A

D

5 days

B

E

3 days

B

F

7 days

C

G

3 days

D, F

H

2 days

E, G

I

1 day

H

• Draw the network as a Gantt chart.

• What is the critical path? Which activities have slack time?

• What would happen if activities B and D each took 5 extra days to complete instead of the expected duration? How would the critical path change?

The response must include a reference list. Using Times New Roman 12 pnt font, double-space, one-inch margins, and APA style of writing and citations.

Request for Solution File

Ask an Expert for Answer!!
Business Management: What is the estimated total duration for the project
Reference No:- TGS03075154

Expected delivery within 24 Hours