What is the critical path what is the expected project


The following represents a project that should be scheduled using CPM:

Activity   Immediate Predecessors Times(days)

                                                 a      m      b

A                     -                    1    3    5           

B                    -                      1            2     3

C                     A                    1            2     3

D                     A                    2            3     4

E                    B                    3              4    11

F                     C,D                3              4     5

G                     D,E                1             4      6

H                     F,G                 2             4      5

a. Draw the network.

b. What is the critical path?

c. What is the expected project completion time?

d. What is the probability of completing this project within 16 days?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the critical path what is the expected project
Reference No:- TGS01100740

Expected delivery within 24 Hours