In order to meet holiday demand pennys pie shop requires a


In order to meet holiday demand, penny's pie shop requires a production line that is capable of producing 80 pecan pies per week, while operating only 40 hours per week. there are only 4 steps required to produce a single pecan pie with respective processing times of 3 min, 3 min, 27 min and 8 min.

a) What should be the line's cycle time? How many mins per pie?

b) What is the smallest number of workstations penny could hope for in designing the line considering this cycle time?

c) Suppose that penny finds a solution that requires 2 stations. what would be the efficiency of this line?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: In order to meet holiday demand pennys pie shop requires a
Reference No:- TGS01100739

Expected delivery within 24 Hours