What is the cost variance schedule variance cost


Given the following information for a one-year project, answer the following questions.

Planned Value (PV) = $30,000

Earned Value (EV) = $27,000

Actual Cost (AC) = $25,000

Budget at Completion (BAC) = $150,000

What is the cost variance, schedule variance, cost performance index, and schedule performance index for the project?

Is the project ahead of schedule or behind schedule?

Is the project under budget or over budget?

Use the cost performance index to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?

Use the schedule performance index to estimate how long it will take to finish this project.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the cost variance schedule variance cost
Reference No:- TGS01196679

Expected delivery within 24 Hours