What is sunpath multi-factor productivity


Response to the following :

Question 1. 'Order winners' describes a marketing-oriented dimension that is a key to competitive success. Which one of the following is NOT an 'order winner.'

a) Long-term reliability
b) Distinctive desirable product feature
c) Lowest price
d) Highest quality
e) Meets specification Save

Question 2. Reliability is usually described as either short-term or long-term reliability. Short- term reliability problems are usually caused by production problems while long-term reliability problems are usually caused by what>

a) Sales issues
b) Design flaws
c) Warranty costs
d) Poor inspection
e) Poor management practices

Question 3 . In developing an operations strategy, which of the following would be an important product-specific criteria to consider using servitization,

a) After-sale support
b) Price
e) Learning curve
d) Total quaky management
e) Plant-Within-a-Plant (PWP)

Question 4. Typical quality issues include which of the following?

a) Extent of use of outside suppliers
b) Product costing
c) Facility location
d) Organizational structure
e) Defect prevention

Question 5 . Various financial data for SunPath Manufacturing for 2011 & 2012 are shown in the table:

                                                 2411                                                  2412

Output: Sales                            5300,000                                               5330,000

Inputs: Labor                            540,000                                                 543,000

Raw Materials                           545,000                                                 551,000

Energy                                    id="mce_marker"0,000                              59,000

Capital Employed                      5250,000                                                5262,000

Other                                      52,000                                                   56,000

What is SunPath's multi-factor productivity measure in 2012 of "Raw Materials" and "Labor?"

a) 0.28
b) 3.51 0 c) Flexibility
d) 7.67
e) 3.53

Solution Preview :

Prepared by a verified Expert
Operation Management: What is sunpath multi-factor productivity
Reference No:- TGS01864693