What if project team is experiencing schedule delays


Problem: The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path. What should the project manager do in this situation?

  • Review the work breakdown structure (WBS) with the suppliers
  • Discuss the critical path issues with the purchasing department.
  • Escalate the supplier-related issues to the sponsor for resolution.
  • Review the critical path with the stakeholders to define next steps.

Request for Solution File

Ask an Expert for Answer!!
Other Management: What if project team is experiencing schedule delays
Reference No:- TGS03421614

Expected delivery within 24 Hours