What if deliverables are not aligned to the expectations


Problem: A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?

  • Ensure the team understands all additional project requirements.
  • Ensure the team receives continuous feedback from customers/users.
  • Update the project management plan in order to get back on track.
  • Submit a change request to adjust the project scope.

 