What duration in work days is erection estimated to take -


A crew of four workers is scheduled to erect' 40 A-type aluminum shoring towers. Equations [22.13] and [22.14] are applicable for these towers. The towers are 48 ft high. Length of the workday is 8 hr.

a. What duration (in work days) is erection estimated to take?

b. What duration (in work days) is dismantling estimated to take?

c. How would the answers for (a) and (b) change if the high towers were twice the described height?