What are the expected duration variance and standard


What are the expected duration, variance, and standard deviation for an activity whose three time estimates are to = 2, tm = 14, and tp = 14? —show your computations or discuss how you arived at your answers. Just giving the “correct” answers without showing or discussing how you arrived at the “correct” answer will results in a score of zero

Expected duration =

Variance =

Standard deviation=