The earliest expected finish time for a project is 138 days


The earliest expected finish time for a project is 138 days, and its required completion time is 130 days. What is the probability of completing the project before its required time if σt (the standard deviation of the total distribution of the activities on the longest path) is 6?

Show how you arrived at your answer. Just giving the “correct” answers without showing or discussing how you arrived at the “correct” answer will results in a score of zero.