What are the different paths to finish the project


Problem

You Have Been Asked To Complete A Project In The Shortest Time Possible. The Project Tasks' Duration (In Days), And Predecessors Are Shown Below.

Tasks Duration

You have been asked to complete project in the shortest time possible. The project tasks' duration (in days), and predecessors are shown below.

Tasks

Duration

Predecessors

A

2

None

B

2

None

C

1

None

D

4

A

E

5

B

F

1

C, D

G

6

A, E

H

4

F

I

7

G, H

Answer the following questions:

A. Which activities have highest and lowest slacK?

B. What are the different paths (sequence of tasks) to finish the above project and how many days does each path task?

C. What is the critical path, i.e., the shortest time in which the above whole project can be completed?

D. As a Project manager, what can you do to speedup project

Request for Solution File

Ask an Expert for Answer!!
Project Management: What are the different paths to finish the project
Reference No:- TGS03323034

Expected delivery within 24 Hours