Using the following information below calculate the cost


Earned Value Exercise

Complete the following problems:

1. The following project is at the end of its first week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

2

550

700

100

B

None

3

950

1450

100

C

A

2

300

350

50

D

A

5

700

650

20

E

B ,C

6

1000

350

10

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________

CPI ________________

SV ______________________

SPI ________________

EAC _____________________

2. Using the following information below, calculate the cost performance index and the schedule performance index. Then calculate the estimate at completion
Planned value: 7700
Earned value: 7100
Actual costs: 7900
Budget at completion: 39900

CPI _______________________

SPI _____________________________

EAC ______________________

3. The following project is at the end of its third week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

3

700

750

100

B

A

5

1100

1400

100

C

A

2

250

300

100

D

A

5

900

600

100

E

B ,C

6

1300

1200

100

F

C

10

11000

12500

75

G

F

7

900

0

0

H

G

8

1500

0

0

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________

CPI ________________

SV ______________________

SPI ________________

EAC _____________________

4. Mary is the project manager for a web design project for Newberry Pet Foods. So far in the six weeks (of the twelve week project), Mary's team has completed five tasks which had a combined planned value of $8800. However, the team spent $9200 to complete those tasks. She has five additional tasks to complete the project. What are the PV, EV, AC, CV, SV, CPI, and SPI for Mary's project?

5. Consider the following information:

PV=6700

EV=5200

AC=7400

BAC=32000

Expected Duration=12 weeks

Calculate the following:

CV __________________

SV __________________

CPI __________________

SPI __________________

EAC __________________

Duration at Completion _______________